{"id":4951,"date":"2026-11-04T11:05:25","date_gmt":"2026-11-04T03:05:25","guid":{"rendered":"https:\/\/ufreight.com\/?p=4951"},"modified":"2026-11-04T16:29:20","modified_gmt":"2026-11-04T08:29:20","slug":"korea-greece-oversized-egcs-project-cargo","status":"publish","type":"post","link":"https:\/\/ufreight.com\/cn\/korea-greece-oversized-egcs-project-cargo\/","title":{"rendered":"Oversized Marine Equipment Shipping from Korea to Greece: An EGCS Project Cargo Case"},"content":{"rendered":"<p class=\"wp-block-paragraph\">Oversized marine equipment shipping from Korea requires careful coordination from the first route review to the final delivery. At U-Freight Korea, we recently worked on a separate project involving an Exhaust Gas Cleaning System, or EGCS, moving from Korea to Athens, Greece. The project required two 40-foot flat-rack containers, cargo preparation, flat-rack loading, lashing supervision and ocean freight coordination with an overseas logistics partner. This is how we approached the project and the main points we considered as the large marine equipment moved internationally.<\/p>\n\n\n\n<figure class=\"wp-block-video\"><video height=\"1080\" style=\"aspect-ratio: 1440 \/ 1080;\" width=\"1440\" controls src=\"https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/OOG-video.mp4\"><\/video><\/figure>\n\n\n\n<h2 class=\"wp-block-heading\">Why EGCS equipment needs project cargo planning<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">An EGCS, also known as a marine exhaust gas scrubber system, is not ordinary containerised cargo when the equipment is large or oversized. The dimensions, weight, lifting points, centre of gravity, packing, securing method and final delivery location all affect the transport plan.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">For a project like this, we need to look beyond the ocean freight booking. Our planning can involve:<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Reviewing cargo dimensions, weights and technical information<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Checking the origin route and export-port requirements<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Selecting suitable flat-rack equipment<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Preparing the cargo for lifting and transport<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Coordinating flat-rack loading<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Reviewing securing and lashing requirements<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Supervising the agreed loading and lashing work<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Coordinating ocean freight and project milestones<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Reviewing customs, port handling and final delivery requirements<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The equipment, carrier, port, container and final delivery arrangements need to work together. A vessel service alone does not confirm that an oversized shipment can be accepted or delivered.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Our <a href=\"https:\/\/ufreight.com\/cn\/freight-forwarding-services\/\" rel=\"noopener\" target=\"_blank\"><img decoding=\"async\" alt=\"\" src=\"https:\/\/api.manus.im\/api\/website_tool\/fetch_website_favicon?host=ufreight.com\">freight forwarding services<\/a> cover import, export and international forwarding coordination. For OOG marine equipment, we review the actual cargo and route before confirming the service scope.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">Our EGCS project from Korea to Athens<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">The project involved an EGCS manufactured in Korea and shipped to Athens, Greece, in cooperation with an overseas logistics partner. This was a separate project from our ongoing ship-spares and ICN warehouse work.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The equipment required two 40-foot flat-rack containers. One unit was approximately 9.2 metres in length and the second was approximately 6.9 metres in length. The combined project volume was approximately 200 CBM. We are using rounded figures here; the final dimensions, weights and loading arrangement were reviewed for the actual shipment.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The project required us to coordinate several activities rather than treat the shipment as a standard container booking. We reviewed the route, prepared the cargo information, coordinated flat-rack loading, followed the lashing arrangements and aligned the ocean freight movement with the origin and destination requirements.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Every large marine equipment project has its own constraints. The final plan depends on the actual packed dimensions, gross weight, lifting points, equipment availability, carrier acceptance, port rules and destination handling. The same arrangement cannot simply be copied to another EGCS or marine system.<\/p>\n\n\n\n<figure class=\"wp-block-gallery has-nested-images columns-default is-cropped wp-block-gallery-1 is-layout-flex wp-block-gallery-is-layout-flex\">\n<figure class=\"wp-block-image size-large\"><img decoding=\"async\" width=\"1024\" height=\"768\" data-id=\"4956\" data-src=\"https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145051_30_28-1024x768.jpg\" alt=\"cargo lifting points 2\" class=\"wp-image-4956 lazyload\" data-srcset=\"https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145051_30_28-1024x768.jpg 1024w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145051_30_28-300x225.jpg 300w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145051_30_28-768x576.jpg 768w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145051_30_28-1536x1152.jpg 1536w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145051_30_28-16x12.jpg 16w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145051_30_28-scaled.jpg 667w\" data-sizes=\"(max-width: 1024px) 100vw, 1024px\" src=\"data:image\/svg+xml;base64,PHN2ZyB3aWR0aD0iMSIgaGVpZ2h0PSIxIiB4bWxucz0iaHR0cDovL3d3dy53My5vcmcvMjAwMC9zdmciPjwvc3ZnPg==\" style=\"--smush-placeholder-width: 1024px; --smush-placeholder-aspect-ratio: 1024\/768;\" \/><figcaption class=\"wp-element-caption\">cargo lifting points 2<\/figcaption><\/figure>\n\n\n\n<figure class=\"wp-block-image size-large\"><img decoding=\"async\" width=\"667\" height=\"500\" data-id=\"4953\" data-src=\"https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145049_29_28.jpg\" alt=\"cargo lifting points\" class=\"wp-image-4953 lazyload\" data-srcset=\"https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145049_29_28.jpg 667w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145049_29_28-300x225.jpg 300w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145049_29_28-768x576.jpg 768w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145049_29_28-16x12.jpg 16w\" data-sizes=\"(max-width: 667px) 100vw, 667px\" src=\"data:image\/svg+xml;base64,PHN2ZyB3aWR0aD0iMSIgaGVpZ2h0PSIxIiB4bWxucz0iaHR0cDovL3d3dy53My5vcmcvMjAwMC9zdmciPjwvc3ZnPg==\" style=\"--smush-placeholder-width: 667px; --smush-placeholder-aspect-ratio: 667\/500;\" \/><figcaption class=\"wp-element-caption\">cargo lifting points<\/figcaption><\/figure>\n\n\n\n<figure class=\"wp-block-image size-large\"><img decoding=\"async\" width=\"1024\" height=\"768\" data-id=\"4954\" data-src=\"https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145025_25_28-1024x768.jpg\" alt=\"loading the flat racks\" class=\"wp-image-4954 lazyload\" data-srcset=\"https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145025_25_28-1024x768.jpg 1024w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145025_25_28-300x225.jpg 300w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145025_25_28-768x576.jpg 768w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145025_25_28-1536x1152.jpg 1536w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145025_25_28-16x12.jpg 16w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145025_25_28-scaled.jpg 667w\" data-sizes=\"(max-width: 1024px) 100vw, 1024px\" src=\"data:image\/svg+xml;base64,PHN2ZyB3aWR0aD0iMSIgaGVpZ2h0PSIxIiB4bWxucz0iaHR0cDovL3d3dy53My5vcmcvMjAwMC9zdmciPjwvc3ZnPg==\" style=\"--smush-placeholder-width: 1024px; --smush-placeholder-aspect-ratio: 1024\/768;\" \/><figcaption class=\"wp-element-caption\">loading the flat racks<\/figcaption><\/figure>\n\n\n\n<figure class=\"wp-block-image size-large\"><img decoding=\"async\" width=\"1024\" height=\"768\" data-id=\"4955\" data-src=\"https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145015_19_28-1024x768.jpg\" alt=\"loading the flat racks 2\" class=\"wp-image-4955 lazyload\" data-srcset=\"https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145015_19_28-1024x768.jpg 1024w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145015_19_28-300x225.jpg 300w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145015_19_28-768x576.jpg 768w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145015_19_28-1536x1152.jpg 1536w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145015_19_28-16x12.jpg 16w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145015_19_28-scaled.jpg 667w\" data-sizes=\"(max-width: 1024px) 100vw, 1024px\" src=\"data:image\/svg+xml;base64,PHN2ZyB3aWR0aD0iMSIgaGVpZ2h0PSIxIiB4bWxucz0iaHR0cDovL3d3dy53My5vcmcvMjAwMC9zdmciPjwvc3ZnPg==\" style=\"--smush-placeholder-width: 1024px; --smush-placeholder-aspect-ratio: 1024\/768;\" \/><figcaption class=\"wp-element-caption\">loading the flat racks 2<\/figcaption><\/figure>\n\n\n\n<figure class=\"wp-block-image size-large\"><img decoding=\"async\" width=\"1024\" height=\"768\" data-id=\"4957\" data-src=\"https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145021_23_28-1024x768.jpg\" alt=\"Lashing supervision\" class=\"wp-image-4957 lazyload\" data-srcset=\"https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145021_23_28-1024x768.jpg 1024w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145021_23_28-300x225.jpg 300w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145021_23_28-768x576.jpg 768w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145021_23_28-1536x1152.jpg 1536w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145021_23_28-16x12.jpg 16w, https:\/\/ufreight.com\/wp-content\/uploads\/2026\/11\/\u5716\u7247_20261027145021_23_28-scaled.jpg 667w\" data-sizes=\"(max-width: 1024px) 100vw, 1024px\" src=\"data:image\/svg+xml;base64,PHN2ZyB3aWR0aD0iMSIgaGVpZ2h0PSIxIiB4bWxucz0iaHR0cDovL3d3dy53My5vcmcvMjAwMC9zdmciPjwvc3ZnPg==\" style=\"--smush-placeholder-width: 1024px; --smush-placeholder-aspect-ratio: 1024\/768;\" \/><figcaption class=\"wp-element-caption\">Lashing supervision<\/figcaption><\/figure>\n<\/figure>\n\n\n\n<h2 class=\"wp-block-heading\">Route planning from Korea to Greece<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">For the Korea-to-Greece movement, we considered how the equipment would travel from the manufacturing location to the export port, how it would be loaded on the flat racks and how the units would be handled on arrival in Greece.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">A route review for OOG cargo may include:<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Road access from the factory or project site<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Oversized transport restrictions and permits<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Crane and lifting requirements<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Flat-rack availability and technical suitability<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Port receiving rules and terminal cut-off times<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Ocean carrier acceptance and vessel space<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Securing and lashing requirements<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Transshipment or connection risks<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Import customs and destination documents<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Final delivery access and lifting arrangements<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The shortest route is not always the best route for oversized marine equipment. We need to consider whether the ports, carrier, equipment and final delivery team can handle the cargo safely and within the required time window.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">This is also why early technical information matters. A change in height, packing, lifting point or delivery address can affect the route, equipment and cost.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">Preparing the cargo and loading the flat racks<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Cargo preparation starts with the right information. For EGCS and other marine equipment, we may need technical drawings, photographs, packed dimensions, gross weight, centre of gravity, lifting points and manufacturer or cargo-owner instructions.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Before loading, the team needs to understand how the equipment will be lifted, positioned and secured. Flat-rack loading may involve checking the payload, protecting vulnerable parts, confirming clearances, positioning the equipment according to the agreed plan and recording the cargo condition.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The larger and smaller units in this project were reviewed according to their own dimensions and handling requirements. One loading plan should not be assumed to apply to every piece of equipment, even when the units belong to the same system.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Our job is to bring the cargo information, equipment plan, loading team and freight milestones together. The technical responsibility remains with the appropriate cargo owner, engineer, surveyor or appointed contractor where those parties are required for the project.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">Lashing supervision and ocean freight coordination<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Lashing is a key part of an OOG movement because the cargo may experience lifting, terminal handling, road transport and vessel movement before it reaches the destination. The securing method needs to reflect the equipment\u2019s weight distribution, centre of gravity, securing points, flat-rack characteristics and carrier requirements.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">For this project, lashing supervision formed part of the preparation before the cargo moved into the ocean freight stage. We coordinated with the relevant teams, followed the agreed securing arrangement and raised any issue that needed attention before the cargo proceeded.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Ocean freight coordination connects the project milestones. Flat-rack release, cargo readiness, loading, lashing, terminal receiving, customs documentation and vessel cut-off all need to align. If one stage changes, the next stage may also need to be reviewed.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Our <a href=\"https:\/\/ufreight.com\/cn\/logistics-distribution\/\" rel=\"noopener\" target=\"_blank\"><img decoding=\"async\" alt=\"\" src=\"https:\/\/api.manus.im\/api\/website_tool\/fetch_website_favicon?host=ufreight.com\">international logistics and distribution services<\/a> include ocean freight, customs clearance, warehousing and cargo supervision. For a project like this, we confirm which party is responsible for technical checks, customs, port handling, freight and final delivery.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">What we learned from this project<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">This EGCS project reinforced several points that we apply to oversized marine equipment planning:<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022OOG cargo should be reviewed before the booking is treated as confirmed.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Flat-rack availability can affect the shipping plan.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Cargo preparation is directly linked to loading and lashing.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Each unit needs its own dimensions, weight and handling review.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Port and terminal requirements are part of the route plan.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Destination handling should be considered before origin loading.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Approximate figures are not a replacement for final technical data.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The project also shows the difference between moving a standard container and coordinating marine project cargo. A successful plan needs the right information and the right parties involved at each stage.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">Information we need for an OOG assessment<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">If you are planning to move EGCS equipment or other oversized marine machinery from Korea, please provide the following where available:<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Equipment description and intended use<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Final packed dimensions and gross weight<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Number of units and proposed container type<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Technical drawings or photographs<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Lifting points, centre of gravity and handling instructions<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Packing, crating and protection details<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Origin and destination addresses<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Export and destination ports<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Required shipping date and delivery deadline<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Importer, consignee and customs information<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Required lifting, storage, port or final-mile services<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2022Carrier, shipyard, terminal or engineering instructions<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The earlier we receive this information, the more time the relevant parties have to review the route, equipment, port and carrier constraints. The plan may still need to change if final dimensions, packing or delivery conditions change.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">Request an oversized marine equipment assessment<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Planning to ship EGCS equipment or other oversized marine machinery from Korea? <a href=\"https:\/\/ufreight.com\/cn\/locations\/\" rel=\"noopener\" target=\"_blank\"><img decoding=\"async\" alt=\"\" src=\"https:\/\/api.manus.im\/api\/website_tool\/fetch_website_favicon?host=ufreight.com\">Contact U-Freight through our locations page<\/a> with the cargo description, packed dimensions, weight, drawings or photographs, origin, destination, preferred shipping date and final delivery requirements. We can review whether your project may require route planning, flat-rack containers, cargo preparation, lashing supervision, ocean freight coordination or destination-side handling.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Share the project details with us early so we can review the practical options with the relevant teams. Equipment, carrier space, port handling, customs, lashing scope and delivery timing are confirmed for the specific project.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">Frequently Asked Questions<\/h2>\n\n\n<div id=\"rank-math-faq\" class=\"rank-math-block\">\n<div class=\"rank-math-list\">\n<div id=\"faq-question-1793760467364\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question\">What is an EGCS in marine project cargo?<\/h3>\n<div class=\"rank-math-answer\">\n\n<p>EGCS stands for Exhaust Gas Cleaning System. It is marine equipment associated with the treatment of vessel exhaust gases and may include large components that require specialist transport planning. The shipping requirements depend on the final equipment configuration, packed dimensions, weight, lifting points and securing instructions.<\/p>\n\n<\/div>\n<\/div>\n<div id=\"faq-question-1793760472416\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question\">Can an EGCS move in standard containers?<\/h3>\n<div class=\"rank-math-answer\">\n\n<p>Some components may fit standard equipment, but a large system or major component may require flat-rack or another specialist transport solution. The decision depends on the packed dimensions, weight, clearances, lifting method, carrier acceptance and port-handling capability. We review the equipment before confirming the container type.<\/p>\n\n<\/div>\n<\/div>\n<div id=\"faq-question-1793760477960\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question\">Why is lashing supervision important for oversized marine equipment?<\/h3>\n<div class=\"rank-math-answer\">\n\n<p>Lashing and securing help control the cargo during lifting, terminal handling, road movement and ocean transport. The method must reflect the cargo\u2019s weight distribution, centre of gravity, securing points, flat-rack characteristics and carrier requirements. We coordinate the agreed loading and securing process with the relevant cargo, engineering, carrier and handling teams.<\/p>\n\n<\/div>\n<\/div>\n<div id=\"faq-question-1793760485872\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question\">Is approximately 200 CBM a standard volume for an EGCS project?<\/h3>\n<div class=\"rank-math-answer\">\n\n<p>No. Approximately 200 CBM refers to the rounded volume of the project described in this article. EGCS systems vary in design, configuration, packing and dimensions. Each project requires its own measurements, drawings, weights, loading plan and equipment assessment.<\/p>\n\n<\/div>\n<\/div>\n<\/div>\n<\/div>","protected":false},"excerpt":{"rendered":"<p>Oversized marine equipment shipping from Korea requires careful coordination from the first route review to the final delivery. At U-Freight Korea, we recently worked on a separate project involving an Exhaust Gas Cleaning System, or EGCS, moving from Korea to Athens, Greece. The project required two 40-foot flat-rack containers, cargo preparation, flat-rack loading, lashing supervision&#8230;<\/p>","protected":false},"author":2,"featured_media":4952,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"content-type":"","om_disable_all_campaigns":false,"_monsterinsights_skip_tracking":false,"footnotes":""},"categories":[74],"tags":[],"class_list":["post-4951","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-blog"],"_links":{"self":[{"href":"https:\/\/ufreight.com\/cn\/wp-json\/wp\/v2\/posts\/4951","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/ufreight.com\/cn\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/ufreight.com\/cn\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/ufreight.com\/cn\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/ufreight.com\/cn\/wp-json\/wp\/v2\/comments?post=4951"}],"version-history":[{"count":4,"href":"https:\/\/ufreight.com\/cn\/wp-json\/wp\/v2\/posts\/4951\/revisions"}],"predecessor-version":[{"id":4962,"href":"https:\/\/ufreight.com\/cn\/wp-json\/wp\/v2\/posts\/4951\/revisions\/4962"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/ufreight.com\/cn\/wp-json\/wp\/v2\/media\/4952"}],"wp:attachment":[{"href":"https:\/\/ufreight.com\/cn\/wp-json\/wp\/v2\/media?parent=4951"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/ufreight.com\/cn\/wp-json\/wp\/v2\/categories?post=4951"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/ufreight.com\/cn\/wp-json\/wp\/v2\/tags?post=4951"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}